An Arkona construction company will oversee the second phase of Huron Street’s reconstruction in Stratford.
On Monday night, Stratford city council vote unanimously in favour of awarding the project contract to Birnam Excavating Limited, who work in the sewer, watermain, roadbuilding and general contracting industry.
According to a management report by Manager of Engineering Nathan Bottema, the project will affect Huron Street from John Street to Matilda Street.
Crews will replace underground infrastructure, renew the roadway and sidewalks, and upgrade the signalized intersection infrastructure at Foreman Avenue.
Bottema’s report said Birnam’s bid was the lowest of five submitted.
Total cost is $8.6 million including HST.
Construction will begin this year, with an expected Fall 2027 completion date.
Two-way traffic on Huron Street will be maintained in the meantime.